CBI Raids Former J&K Governor Satya Pal Malik’s Premises In Kiru Hydroelectric Project Case
The project is a JV between NHPC, JKSPDC and Power Trading Corporation
Sleuths of Central Bureau of Investigation (CBI) on Thursday began searches in 30 places, including the premises of former Jammu and Kashmir Governor Satya Pal Malik, during its probe into alleged corruption in the awarding of a contract for a hydel project in the Union Territory.
The CBI FIR stated that an investigation had been conducted by the J&K ACB and the power department in the matter. “Perusal of these reports reveals that in award of civil works package of Kiru Hydroelectric Power Project, guidelines regarding e-tendering were not followed and though a decision was taken in the 47th Board Meeting of CVPPPL for re-tender through e-tendering with reverse auction, after cancellation of ongoing tendering process, same was not implemented and the tender was finally awarded to M/s Patel Engineering,” the CBI FIR said.
The project, whose cost is estimated to be Rs 4,287 crore, has been marred by allegations of sub-standard work and its failure to provide jobs to local unemployed youth. The ACB probe into the matter observed that the project’s tender had been cancelled in the 47th Board Meeting of the CVPPPL, but was revived in the 48th Board Meeting and awarded to Patel Engineering.
Kiru hydroelectric power project is a run-of-the-river scheme being developed over the Chenab River in the Kishtwar Tehsil of Doha district in Jammu and Kashmir (J&K), India.
The project is being developed by Chenab Valley Power Projects (CVPP), a joint venture between National Hydroelectric Power Corporation (NHPC, 49%), Jammu & Kashmir State Power Development Corporation (JKSPDC, 49%) and Power Trading Corporation (PTC, 2%).
The estimated investment in the project is Rs. 46.4m ($769m). The project was awarded scoping clearance by Ministry of Environment Forests and Climate Change (MoEF&CC) in September 2008 and revalidated for an installed capacity of 624MW in September 2015.
Environment clearance was issued in June 2016 and the project received approval from the State Administrative Council (SAC) in January 2019. The foundation stone for the hydroelectric power plant was laid in February 2019, while completion is expected by 2023.